Monday, December 18, 2017

Tejas platforms till SP-12 to enter equipping stage soon


By Anantha Krishnan M

Bengaluru, Dec 17: Amidst the ongoing ‘controversy and confusion’ over whether the Indian Air Force (IAF) is keen to go ahead with the home-grown Light Combat Aircraft (LCA) Tejas programme beyond the first and second blocks of 20 each, the sixth series production variant from the hangars of Hindustan Aeronautics Limited (HAL) took to the skies for the first time sans any fanfare, recently.
The maiden flight of SP-7, the sixth out of the total 20 to be delivered in the Initial Operational Clearance (ICO) standards, took place on December 12 at the HAL airport here, with zero snags being reported by the pilot after completing the Profile-1 of the flight envelope.
Tejas SP-7 was piloted by Gp Capt K K Venugopal (Retd). With this, the IAF No 45 Squadron (Flying Daggers) would soon have half-a-dozon of Tejas platforms to operate with. Currently being raised in Bengaluru, the No 45 Squadron will eventually move to Air Force Station Sulur, near Coimbatore.
IAF is ramping up its infrastructure at AFS Sulur with modern hangars being reading to accommodate Tejas 16 fighters and four trainers, part of the first block of delivery from HAL.
SP-5 from Kiran hangar will join the party soon: The fifth Tejas series production platform SP-5, being built at the second production line established at the Aircraft Division by HAL, too will have its maiden flight soon. HAL converted the erstwhile Kiran hangar to set up this additional production line, which boasts of producing three aircraft per year, when fully operational. 
V Sridharan, who retired as the Executive Director of LCA Division recently, says that Tejas platforms up to SP-10 are currently under equipping in Final Assembly Hangar.
“Very soon they will be followed by SP-11 and SP-12. Kudos to the entire Team of Tejas involved in the manufacturing activities for their untiring efforts in making this possible despite adverse criticism in the last three years, both in terms of quality and quantity,” says Sridharan.
Frequent modifications a concern: Interestingly, he says that the even after delivering six series production platforms by HAL, the Standard of Preparation (Build to Print Documents) have not been frozen, despite the IOC nod in December 2013.
“The introduction of more than 270 modifications after accordance of IOC, in the name of concurrent engineering is a potential source of introducing uncertainties during the production phase. This can affect time-lines on a regular basis. These changes even warrant design and manufacturing of new parts which results in delays. All these changes are introduced towards envisaged performance and system improvements as per the requirements of IAF,” says Sridharan, who has been credited with establishing the new LCA Division. 
He says the LCA Division developed ICY (interchangeability) tools for all 147 panels and for 830 pipelines out of 934 pipelines within the build of first seven SP Tejas aircraft itself.
“This is a huge shift compared to any other projects in HAL, that too at such short span of time after the release of RSD (Release of Service Documents). Even now, only concept of replaceable pipes is existing in other projects. LCA has gone far ahead in the area of ICY compliance through the dedicated efforts of its tooling department,” claims Sridharan.
Outsourced all major structural modules: He says HAL, in an effort to further augment the production capacity, has outsourced all the major structural modules to private partners, including sub-assemblies, role equipment, pipelines, sheet metal part electrical looms and panels.
“This would enhance the production rate to 16 per year from the year 2019 onwards apart from developing an eco-system for manufacturing of a 4.5 generation fighter aircraft in India. This is likely to materialize by mid-2018 and thereafter, HAL would further be able to ramp up the production rate to 20 aircraft-plus every year,” adds Sridharan.
On the Final Operational Clearance (FOC) front, sources at Aeronautical Development Agency (ADA) say that the programme will complete all tasks mandated within 2018.
“There are only few more crucial test points to be achieved. Then there could be additional requirements. Hopefully, the FOC should be in place in the third quarter of 2018,” says a top scientist.
Currently, Tejas LSP-8 is optimising flight profiles with the in-flight refueling probe (IFR). The air-to-air refueling trials will begin early 2018. Four Tejas variants recently undertook night attack missions for the first time, as per the FOC schedule. @Mathrubhumi

Friday, December 20, 2013

Tejas squadron formation still a distant dream for IAF | First CO posted For No 45 Sqn at ASTE | Engine test bed readied in Sulur

By Anantha Krishnan M
Express News Service
Bangalore: The Indian Air Force’s (IAF) wait to induct the Tejas might get bit longer till the four series production (SP) aircraft roll out from the brand new hangars of Hindustan Aeronautics Limited (HAL). While today’s second initial operational clearance (IOC-2) will signal the end of a grueling wait for the IAF to officially undertake flight evaluation trials, the formation of No 45 Squadron (Flying Daggers) earmarked for Tejas might take another two more years. The same squadron last flew the MiG 21 Bison aircraft operating from Naliya (Gujarat), an airfield closer to Karachi. The Tejas squadron will eventually be operating from the Sulur air force base, near Coimbatore.
Sources monitoring the Tejas programme said that, HAL’s promise of delivering the first production variant of Tejas (SP-1) by March 2014 might be little far-fetched. “We hope to have the first aircraft by end by mid of 2014. The first two aircraft (SP-1, SP-2) might not meet our standards for squadron formation as the metal cutting and hardware were done before we froze the IOC-2 test points. We will raise the first Tejas squadron with four aircraft starting from SP-3 to SP-6,” a top source said. The IAF will use SP-1 and SP-2 for evaluation flight to be undertaken by the Test pilots of Aircraft System and Testing Establishment (ASTE). The limited series production variants LSP-7 and LSP-8 too will be used for evaluation flights by IAF.
The IAF has already identified the first Commanding Officer for Tejas Squadron, now part of the ASTE team, but he’s yet to fly the Tejas. More officers are expected to join the squadron soon, with only few technicians currently being trained to handle the aircraft. For IAF, the maintainability of Tejas is the most primary concern. “The hardware-related issues need to be fixed first. The software can be upgraded without much delay. The critical factor for any aircraft is its maintainability. Truly speaking, before the IOC event, all hardware must be finalized, which might not still be the case with Tejas,” the source said.
A programme management team from the IAF sits at the Aeronautical Development Agency to ensure that the Tejas comes out as a ‘usable aircraft’ befitting the squadron standards. HAL will deliver first 20 aircraft in IOC configuration and another 20 more in the final operational clearance (FOC) format. Appreciating the safety features of the aircraft, the official said that notwithstanding the delays, the safety features of Tejas was world class. “We are way ahead of F-22, Rafale and Eurofighter. We are very lucky to have a safe Tejas flying today. All other similar programmes had crashes during developmental phase. It is a very creditable achievement,” the official said.
Preparations in Sulur are going as per plans with the engine test bed already being readied. The IAF is awaiting the release of Rs 580 crore from the Ministry of Defence to undertake infrastructure work like taxi tracks, hangars and squadron complex. The IAF Chief Air Chief Marshal N A K Browne on Wednesday (18 December) reviewed the progress of Tejas base in Sulur, during his visit to Thiruvananthapuram.
Copyright@The New Indian Express